In June 2019, RPC Radiy’s engineers performed both acceptance testing and hand-over acceptance testing of several sets of to-be-supplied equipment.

June 5-7, 2019. The Transformer Substation-1000-3 designed for SS South Ukraine NPP Power Unit No.3 Conventional Island I&C System passed hand-over acceptance testing to prove compliance with all Technical Specification requirements.komissiya

June 12-14, 2019. The Power Supply System of Reactor Control and Protection System for SS Rivne NPP Power Unit No.4 successfully passed the hand-over acceptance testing. The results proved the system’s compliance with current Nuclear Radiation Safety rules and standards as well as the Terms of Reference (ToR).isput

June 18-21, 2019. An authorized committee performed the acceptance testing and hand-over acceptance testing of the first supply set of the Engineered Safety Features Actuation System of the second channel (ESFAS-2) for SS South Ukraine NPP Power Unit No.3. The results of testing confirmed the ESFAS-2 meets the requirements of the Terms of Reference (ToR).

All tested equipment is expected to be delivered to the Customers’ sites by the end of July 2019.KTP2

Contact

Project Support Division
T: +38 (0522) 37-33-28
F: +38 (0522) 37-33-28
E: This email address is being protected from spambots. You need JavaScript enabled to view it.

RPC Radiy

Pioneer in the Design, Manufacturing & Installation of FPGA-Based Instrumentation & Control (I&C) Systems

Newsletter Download

Want to recieve news about Radiy’s activities, download our newsletter here or signup to be added to our mailing list.

Newsletter Signup