Social Responsibility: Graduates from Kropyvnytskyi College of Engineering Defend Thesis at PC RPC Radiy
24.06.201914th International Conference on Dependability of Computer Systems DepCoS 2019
05.07.2019In June 2019, RPC Radiy’s engineers performed both acceptance testing and hand-over acceptance testing of several sets of to-be-supplied equipment.
June 5-7, 2019. The Transformer Substation-1000-3 designed for SS South Ukraine NPP Power Unit No.3 Conventional Island I&C System passed hand-over acceptance testing to prove compliance with all Technical Specification requirements.
In June 2019, RPC Radiy’s engineers performed both acceptance testing and hand-over acceptance testing of several sets of to-be-supplied equipment.
June 5-7, 2019. The Transformer Substation-1000-3 designed for SS South Ukraine NPP Power Unit No.3 Conventional Island I&C System passed hand-over acceptance testing to prove compliance with all Technical Specification requirements.
June 18-21, 2019. An authorized committee performed the acceptance testing and hand-over acceptance testing of the first supply set of the Engineered Safety Features Actuation System of the second channel (ESFAS-2) for SS South Ukraine NPP Power Unit No.3. The results of testing confirmed the ESFAS-2 meets the requirements of the Terms of Reference (ToR).
All tested equipment is expected to be delivered to the Customers’ sites by the end of July 2019.