05.07.2019In June 2019, RPC Radiy’s engineers performed both acceptance testing and hand-over acceptance testing of several sets of to-be-supplied equipment.
June 5-7, 2019. The Transformer Substation-1000-3 designed for SS South Ukraine NPP Power Unit No.3 Conventional Island I&C System passed hand-over acceptance testing to prove compliance with all Technical Specification requirements.
In June 2019, RPC Radiy’s engineers performed both acceptance testing and hand-over acceptance testing of several sets of to-be-supplied equipment.
June 5-7, 2019. The Transformer Substation-1000-3 designed for SS South Ukraine NPP Power Unit No.3 Conventional Island I&C System passed hand-over acceptance testing to prove compliance with all Technical Specification requirements.
June 18-21, 2019. An authorized committee performed the acceptance testing and hand-over acceptance testing of the first supply set of the Engineered Safety Features Actuation System of the second channel (ESFAS-2) for SS South Ukraine NPP Power Unit No.3. The results of testing confirmed the ESFAS-2 meets the requirements of the Terms of Reference (ToR).