Position Signaling Mechanisms Undergo Acceptance Testing
19.07.2024Acceptance testing for the VVER-1000 Reactor Control and Protection System (RPS) based on RadICS Platform has been completed at Kozloduy NPP, Bulgaria
26.08.2024July 10-12, 2024 – Radiy conducted testing of new equipment for Rivne Nuclear Power Plant (NPP), which continuously improves its technologies and safety systems. The upgraded equipment for Unit 4 was successfully tested, confirming its quality, innovativeness, and readiness for safe operation.
The Equipment to be delivered to the Customer includes the following:
– Engineered Safety Features Actuation System (ESFAS);
– Electric Distributive Cabinets (EDC) for Safety System 1 of Power Unit 4;
– Level Indication Module;
– Single-turn Electric Actuator MEO-1600/25-0.25-1KA.
The shipment of the accepted equipment will be carried out within the timeframe stipulated in the Supply Contract. By utilizing modern schematic, structural, and software solutions, Rivne NPP will be able to enhance safety levels and improve the efficiency of its operations, ensuring stable and reliable operation of Unit 4, in particular.